For a new Sewer Connection, the customer requests for a connection.This request is made through NAWASCO offices
Ground inspection is carried out to determine the requirement of the new sewer connection.
A report is then prepared which has to be approved by the Technical Manager
A connection requirement is prepared including the material needed and this is communicate to the customer
Once the customer makes the payment, the connection is established
Once complete the account is adjusted so that the customer can receive his/her bill inclusive of the sewer